Hai Phong LNG Power Plant Project

The Hai Phong LNG Thermal Power Plant (LNG Hai Phong) is located in Tan Trao Industrial Park, Hai Phong City, and is jointly developed by Vingroup and VinEnergo, with a total investment of USD 7.7 billion.

The project covers an area of approximately 98.5 hectares, with a designed capacity of 4,800 MW and an estimated annual electricity output of 28.8 billion kWh once fully operational. It will be implemented in two phases:

  • Phase 1: about 1,600 MW, producing 9.6 billion kWh per year
  • Phase 2: about 3,200 MW, producing 19.2 billion kWh per year

Groundbreaking is scheduled for September 26, 2025. Phase 1 is expected to operate during 2025–2030, while Phase 2 is initially planned to come into operation in 2031–2035.

Hai Phong LNG Power Plant