Announcement of Investor for Lien Chieu Container Terminal Project (Component B) in Da Nang

The Lien Chieu Container Terminal Project (Component B) is located in Hai Van Ward, Lien Chieu District, Da Nang, and is developed by a consortium of Hateco GroupHateco Port CompanyAPM Terminals B.V., with a total investment of approximately VND 45,268 billion (around USD 1.76 billion).

The project is being developed on a land area of approximately 146 hectares and nearly 26 hectares of water surface, comprising 08 container berths with a total quay length of approximately 2,750 meters, along with barge berths. The port’s hinterland system includes warehouses, logistics areas, an operations center, and supporting facilities, with a designed throughput capacity of approximately 5.7 million TEU per year.

The project is expected to commence in 2026, with a total implementation period of approximately 10 years, in which Phase 1 (2025–2028) will construct and put into operation at least 02 berths.