Preparation for the Implementation of the High-Quality Care and Treatment Center Project – C Hospital Da Nang


The High-Quality Care and Treatment Center Project of C Hospital Da Nang is located at 122 Hai Phong Street, Hai Chau Ward, Da Nang City, with C Hospital Da Nang as the project owner and a total investment of VND 547 billion.

The project will be developed on a land area of 10,249 square meters, aiming to build a high-quality care and treatment center for C Hospital Da Nang.
The facility will include 10 above-ground floors and 1 basement, with a total gross floor area of 16,625 square meters.

The project is currently in the bidding phase for construction, with contract award results expected to be announced in December 2025 and construction scheduled to commence in early 2026.
The construction period is expected to last 14 months.

C Hospital Da Nang. Image: Baodauthau